Residential development Silicon Valley

PROCESS

February

  • Submission of Final Map Application

  • Submission of Building Permit Application

  • California Environmental Quality Act (CEQA) Passage

July

  • Issuance of demolition permits

  • Asbestos removal and disposal

August

  • Starting Demolition

  • Starting the Department of Real Estate (DRE) Workflow

September

  • Issuance of preliminary draft land grading permit

  • Receive Department of Real Estate (DRE) documents

November

  • Pre-sale

  • Final plat map approved

  • Land Grading Permit Issued

  • Encroachment Permit Issued

December

  • Issuance of building permits

February

  • Submission revised SMP to the county

April

  • Received 2nd Round of Comments on Building Permit

May

  • Site Management Plan Approval

  • Utility Design under review by PG&E

June

  • Rough Grading Permit Issued

July

  • Preparing for Excavation of Contaminated Soil

August

  • 1st Round Excavation

  • 1st Round Lab Analysis

September

  • 2nd Round Excavation

  • 2nd Round Lab Analysis

October

  • 3rd Round Excavation

  • 3rd Lab Result: Samples Free of Chlordane

  • Lot 1-5 Building Permit Approval

November

  • Onsite Improvements Permit Approval

  • Temp Power Pole Installed Onsite

  • Submit SMP Completion Report to DEH

December

  • Lot 5 Building Permit Approval

  • Waiting for County's Approval of SMP Completion Report and Final Map Recordation

January

  • DEH Pass SMP Completion Report

  • Grading Permit Approval

February

  •  Final Map Approval

  • • Construction Starts

  • • Machines to the site

  • • Erosion Control finished

  • • Rough Grading in process

  • • Rough Grading in process

March

  • Soil flattening

  • Stormwater trench excavation & public inspection

  • Underground water supply and drainage layout

  • Bioretention trench and steel reinforcement

April

  • Lot 1-6 bio retension rebar pass inspection & concrete pouring & wall

  • Lot 2/3/4 underfloor plumbing & pass inspection

  • Lot 1-6 Foundation form & rebar & pass inspection

  • VIM in process VIM

May

  • Lot 2/3/4 VIMS completed, foundation inspection passed, concrete pouring completed

  • Lot 2/3/4 framework is being built

June

  • lot 2/3/4

  • 1st floor Framng finish

  • 2nd floor Framng in process
     

July

  • lot 2/3/4

  • 2nd floor Framng & Roof Finish