PROCESS
February
-
Submission of Final Map Application
-
Submission of Building Permit Application
-
California Environmental Quality Act (CEQA) Passage
July
-
Issuance of demolition permits
-
Asbestos removal and disposal
August
-
Starting Demolition
-
Starting the Department of Real Estate (DRE) Workflow

September
-
Issuance of preliminary draft land grading permit
-
Receive Department of Real Estate (DRE) documents
November
-
Pre-sale
-
Final plat map approved
-
Land Grading Permit Issued
-
Encroachment Permit Issued
December
-
Issuance of building permits
February
-
Submission revised SMP to the county
April
-
Received 2nd Round of Comments on Building Permit
May
-
Site Management Plan Approval
-
Utility Design under review by PG&E
June
-
Rough Grading Permit Issued
July
-
Preparing for Excavation of Contaminated Soil
August
-
1st Round Excavation
-
1st Round Lab Analysis
September
-
2nd Round Excavation
-
2nd Round Lab Analysis
October
-
3rd Round Excavation
-
3rd Lab Result: Samples Free of Chlordane
-
Lot 1-5 Building Permit Approval
November
-
Onsite Improvements Permit Approval
-
Temp Power Pole Installed Onsite
-
Submit SMP Completion Report to DEH
December
-
Lot 5 Building Permit Approval
-
Waiting for County's Approval of SMP Completion Report and Final Map Recordation
January
-
DEH Pass SMP Completion Report
-
Grading Permit Approval
February
-
Final Map Approval
-
• Construction Starts
-
• Machines to the site
-
• Erosion Control finished
-
• Rough Grading in process
-
• Rough Grading in process

March
-
Soil flattening
-
Stormwater trench excavation & public inspection
-
Underground water supply and drainage layout
-
Bioretention trench and steel reinforcement

April
-
Lot 1-6 bio retension rebar pass inspection & concrete pouring & wall
-
Lot 2/3/4 underfloor plumbing & pass inspection
-
Lot 1-6 Foundation form & rebar & pass inspection
-
VIM in process VIM

May
-
Lot 2/3/4 VIMS completed, foundation inspection passed, concrete pouring completed
-
Lot 2/3/4 framework is being built

June
-
lot 2/3/4
-
1st floor Framng finish
-
2nd floor Framng in process

July
-
lot 2/3/4
-
2nd floor Framng & Roof Finish